The client was looking for an off-the-shelf solution for their construction company’s wash bay, which would accommodate their fleet of waste removal vehicles and other materials. Citi Industries recently completed a comprehensive wash bay refurbishment in Rocklea, QLD, for a construction company. The existing wash bay set-up was outdated, non-compliant, and presented drainage risks. The objective was to create a compliant and functional washdown solution emphasising sustainability. We designed a solution that upgraded drainage, waste separation, and system control. This transformation improved safety and efficiency across operations.
This blog outlines the history of this project, including its background, challenges, and how the team addressed them with precision and compliance. Let’s begin with the initial issues our client faced.

Problems
The original wash bay facility in Rocklea was plagued with structural and compliance issues from the outset. For one, there was no oil-water separator installed. Secondly, the drainage system was failing, causing water to pool. And thirdly, there was a huge contamination risk with no backflow prevention whatsoever.
On top of that, the existing slab was substandard concerning gradient. There was no venting, no pump well, and no practical way to separate solids from the wastewater.
With all of the issues mentioned above, the wash bay could not meet AS/NZS plumbing codes. These failures also violated environmental standards. There was, therefore, the need for rapid, safe, and professional intervention from our side.
In light of the identified problems, the next step was to deliver a complete and compliant solution.

Solutions
Our team provided a tailored-made solution, with the help of our partners, to carry out a step-by-step to upgrade the wash bay system fully system:
- Demolition and Site Works
- Demolished the triple interceptor and old concrete slab.
- Trenches for new drainage placement were excavated and compacted.
- Drainage and Plumbing Works
- A Fox FX1000SS Oil/Water Separator was installed.
- An Ultra Flow 1200L Pump Well was installed, enhancing the wastewater infrastructure.
- 100mm DWV pipes and HDPE stormwater lines were plumbed to connect to existing services.
- Compliance and control works the Reduced Pressure Zone Device (RPZD) was installed for safe water backflow protection.
- The diaphragm pump was installed with a float switch for level automation.
- A weatherproof control panel with GPOs has been installed.
- Fines and Signage A new concrete slab was formed at 1:80 gradient to the silt trap.
- Installed a grate and silt basket.
- Making sure there’s a mounted “non-potable water” signage and vent piping.
This wash bay renovation in Rocklea, QLD, delivered a modern, efficient, and safe washdown facility.
Why Choose Citi Industries for Your Wash Bay Renovation, Plumbing, or Pump Well Installation?
We not only provide renewal but also offer solutions that deliver long-term performance. Our wash bay systems meet all Australian Standards. Under one roof, we bring plumbing, drainage and electrical works together for the best result.
Australian suppliers are trusted, and material selection is based on durability, compliance, and environmental considerations. All silt traps, pumps, wells, and separators are rightly done.
With certified quality and operational excellence, every wash bay renovation in Rocklea, QLD.
Is it time to upgrade your wash bay or drainage system?
Citi Industries specialises in turn-key plumbing, drainage, and water-management solutions. Whatever terrain leveling you need, pump wells, or oil/water separators, we do it all. Call our team for your wash bay assessment today.