• CALL 1300 002 484
  • Email Us >>
  • Skip to main content
  • Skip to primary sidebar
Citi Industries

Citi Industries

Email Us
  • Services
  • Products
  • Resources
  • Case Studies
  • About
  • Contact
    • Wash Bay Construction FIND OUT MORE
    • Grease Trap Installation FIND OUT MORE
    • Grease Trap Lid Installation FIND OUT MORE
    • Plumbing Installation FIND OUT MORE
      • Storm Water Installation FIND OUT MORE
      • Hot Water Systems FIND OUT MORE
      • Gasfitting FIND OUT MORE
      • Backflow DevicesFIND OUT MORE
      • Commercial Plumbing FIND OUT MORE
      • Industrial Plumbing Design FIND OUT MORE
    • Plumbing Design FIND OUT MORE
  • Grease Trap RangeFIND OUT MORE
    • Above Ground CHECK SIZES
    • Below Ground CHECK SIZES
    • LID REPLACEMENT FIND OUT MORE
    • Regulations FIND COUNCIL RULES
    • Pumps CHECK SIZES
    • Septic Tanks GET A QUOTE
  • Pump Stations FIND OUT MORE
    • Sewer Pump Stations CHECK SIZES
    • Storm Water Pump Stations CHECK SIZES
    • Diaphragm Pumps CHECK SIZES
  • Oil Water Separators CHECK SIZES
  • Holding Tanks CHECK SIZES
  • Grease Trap Lids CHECK SIZES
  • Grease Trap Regulations FIND OUT MORE
  • News & Insight FIND OUT MORE
  • About
  • Wash Bays
    • Oil Water Separators
    • Sewer Pump Stations
    • Diaphragm Pumps
    • Bunding
    • Wash Bay Design
  • Grease Traps
    • Above Ground
    • Below Ground
    • Lid Repairs
    • FIND COUNCIL RULES
    • Pumps
    • Septic Tanks
  • Plumbing
    • Commercial Plumbing
    • Industrial Plumbing
    • Stormwater
    • Hot Water
    • Gasfitting
    • Backflow Devices
    • Plumbing Design
  • Case Studies
  • Contact

Trade Waste and Plumbing Installation for a Brisbane Craft Brewery

Client: Craft Brewery based in Brisbane, Queensland

Trade waste plumbing brewery installation showing internal above-slab drainage pipework and trade waste connections at a craft brewery fit-out in Brisbane, Queensland.

Opening a craft brewery is one thing. Getting the plumbing right behind the scenes is another.

Brewing operations generate significant volumes of trade waste. This includes spent grain, rinse water, cleaning chemicals, yeast byproducts and general kitchen wastewater. All of it needs somewhere compliant to go. Without proper brewery plumbing from the start, a new venue faces compliance problems at the worst possible time.

A Brisbane craft brewery faced exactly this challenge. As part of a new venue fit-out, they needed a complete trade waste solution. The scope covered internal above-slab drainage, trade waste pipework, atmospheric venting, and cold water supply to the kitchen. Additionally, the work had to integrate with an existing holding tank. The site also required zero roof penetrations, which shaped the entire approach.

Citi Industries delivered the full scope.

Project Overview

This brewery fit-out came with a specific constraint from day one: no roof penetrations.

The venue needed a complete plumbing system built around an existing holding tank. This covered internal above-slab trade waste drainage, trade waste pipework, atmospheric venting, and cold water supply to the kitchen. That constraint shaped the entire approach.

Key project objectives included:

  • Trade waste plumbing installation connecting the holding tank
  • Internal above-slab drainage for trade waste throughout the venue
  • All vents routed to atmosphere via the rear building face, over the gutter
  • A 15mm RPZD backflow prevention valve on the cold water supply
  • Cold water supply connection to the kitchen

Commercial brewery drainage system installation showing holding tank connection, atmospheric venting, and brewery plumbing installation works at a craft brewery in Brisbane, Queensland.

Challenges

Craft breweries with commercial kitchens fall under Queensland’s trade waste requirements. Brewing operations, cleaning processes, and kitchen activities all generate wastewater. This wastewater must flow through compliant infrastructure before it enters the sewer network.

Queensland Urban Utilities guidelines are clear. Businesses need approved hydraulic plans and compliant pre-treatment infrastructure before they can discharge trade waste.

For this venue, the team designed the internal drainage layout to capture trade waste from all fixtures. Every drainage line, junction, and vent required precise positioning. The existing slab dictated the constraints for achieving correct falls and flow paths.

Two further requirements shaped the scope. First, roof penetrations were not permitted. This meant venting had to run up the rear face of the building to the atmosphere. The route went over the gutter without compromising the building fabric. Second, backflow prevention on the cold water supply was mandatory. An RPZD valve protects the potable supply from cross-contamination where water lines run alongside trade waste infrastructure.

Key challenges included:

  • Designing internal above-slab drainage with correct falls and flow paths, within slab constraints
  • Routing all vents to atmosphere via the rear building face, with no roof penetrations
  • Connecting trade waste pipework correctly to the existing holding tank
  • Installing backflow prevention on the cold water supply to the kitchen
  • Delivering all works on schedule as part of a live venue fit-out

Three-panel site photo showing grease trap and trade waste pipework installation at a craft brewery in East Brisbane QLD, including drainage pit excavation with pipe stubs, below-slab pipework connections, and internal above-slab drainage works along the building wall.

What Was Delivered

Citi Industries delivered a complete commercial brewery drainage system. This covered all internal trade waste drainage, pipework, venting, and cold water supply. The result: a fully operational and compliant venue.

Internal Above-Slab Trade Waste Drainage

The team installed all drainage lines above the slab. Each line achieved correct gradients and flow paths throughout the tenancy.

In a brewery environment, getting this right matters. Incorrectly graded drainage lines lead to blockages. In a venue open to the public, that creates both operational and compliance problems.

Trade Waste Pipework and Tank Connection

The team installed all trade waste pipework to connect the internal drainage network to the existing holding tank. Every junction followed the correct sequence. This ensures trade waste flows through the system without bypassing any part of the approved infrastructure.

Atmospheric Venting: Rear Face of Building

The team ran all vents up the rear face of the building to the atmosphere, over the gutter line. The installation required no roof penetrations.

Proper venting is non-negotiable in a commercial kitchen trade waste system. Without it, trap seals siphon. Odours enter the building. Drainage performance degrades over time.

Cold Water Supply and Backflow Prevention

The team connected cold water supply to the kitchen and installed a 15mm RPZD backflow prevention valve on the supply line.

All plumbing works met the National Construction Code Volume Three, Plumbing Code of Australia. This code sets minimum standards for brewery plumbing across commercial facilities in Australia.

Six-panel photo showing completed brewery plumbing installation in East Brisbane QLD including atmospheric vent on rear building face, above-slab trade waste pipework, RPZD backflow prevention valve on cold water supply, grease trap connections, and completed drainage layout along the building wall.

Final Outcome

The project finished on schedule. The brewery opened with a correctly built drainage system before serving a single customer.

Getting plumbing right during a fit-out matters. Revisiting it after the venue is trading means managing compliance problems under operational pressure. This installation delivered exactly what the venue needed: a compliant, fully connected trade waste system ready from day one.

The project delivered:

  • A compliant above-slab brewery wastewater system that captures trade waste from all kitchen and brewing fixtures
  • Atmospheric venting via the rear building face, with no roof penetrations
  • A 15mm RPZD backflow prevention valve protecting the potable cold water supply
  • Trade waste pipework correctly connected to the holding tank, matching the approved hydraulic design

Queensland Urban Utilities trade waste guidelines require compliant trade waste infrastructure for any brewery or commercial kitchen in Queensland. This project delivered exactly that.

Partner With Citi Industries for Your Brewery or Commercial Kitchen Plumbing

Fitting out a new craft brewery? Upgrading trade waste infrastructure? Navigating Queensland’s compliance requirements for the first time? Citi Industries has the expertise to get it done right.

  • Talk to us about trade waste plumbing installation and whether you are fitting out a new venue or upgrading an existing one, we know what compliant brewery plumbing looks like.
  • Find out about our commercial plumbing services covering cold water supply, backflow prevention, sanitary drainage, and more.
  • See our industrial drainage solutions for complex projects across commercial and industrial environments in Queensland.

Call us on 1300 002 484 Monday to Friday, 7am to 6pm, or send us your details online and we will take it from there.

Primary Sidebar

BROCHURE

Wash Bay Design
& Construct

OPEN & DOWNLOAD NOW

BROCHURE

Grease Trap
Supply & Install

OPEN & DOWNLOAD NOW

BROCHURE

Commercial
Plumbing

OPEN & DOWNLOAD NOW

BROCHURE

Hydraulic
Design

OPEN & DOWNLOAD NOW

Product categories

  • Septic Tanks
  • Hydraulic Design Products
  • Industrial and Commercial Grease Trap Products
    • Above Ground
    • Below Ground
  • Bollards
  • Safety Mirrors
  • Speed Humps
  • Wheel Stops & Chocks
  • Pumps Stations
    • Diaphragm Pumps
    • Sewer Pump Stations
    • Stormwater Pump Stations
  • Oil Water Separators

BROWSING HISTORY

  • 800MM STAINLESS STEEL OUTDOOR CONVEX SAFETY MIRROR 800MM STAINLESS STEEL OUTDOOR CONVEX SAFETY MIRROR
  • 1500 LITRE VIKING PT ABOVE GROUND GREASE TRAP 1500 LITRE VIKING PT ABOVE GROUND GREASE TRAP
  • 3000 LITRE HALGAN BELOW GROUND GREASE TRAP 3000 LITRE HALGAN BELOW GROUND GREASE TRAP

INFORMATION

  • About Us
  • Contact Us

SEE HOW WE CAN HELP WITH YOUR PROJECT

  • This field is for validation purposes and should be left unchanged.

GIVE US A CALL

1300 002 484

MON-FRI | 7am – 6pm

Check out our Products
and Services

  • Wash Bays
  • Grease Traps
  • Plumbing

Home

  • About
  • Case Studies
  • Grease Traps
  • Blog
  • Wash Bays
  • Contact Us
  • Plumbing

MY ACCOUNT

  • Security Policy
  • Privacy Policy
  • Returns Policy
  • Conditions of Use

We Accept

LET’S CONNECT

  • Facebook
  • Twitter
  • Instagram

PO Box 1449, Coorparoo QLD 4151
1300 002 484
© CitiIndustries.com.au | All Rights Reserved | Sitemap

Our Spring Sale Has Started

You can see how this popup was set up in our step-by-step guide: https://wppopupmaker.com/guides/auto-opening-announcement-popups/

Get the latest
free ebook

brochure title here


  • This field is for validation purposes and should be left unchanged.

Privacy Policy

  • This field is for validation purposes and should be left unchanged.
  • SUBMIT YOUR ENQUIRY AND WE WILL RESPOND SHORTLY

    Trade Waste and Plumbing Installation for a Brisbane Craft Brewery

  • This field is hidden when viewing the form
  • If you prefer you can call us on 1300 002 484 Mon-Fri 7am-6pm